Many ADU projects take about 3 to 9 months from design to move-in.
Individual jobs vary, and the type of ADU, your site and your city all
affect it.
The main stages:
-
1
Planning and plans: we look
at your property, and your plans can come from your own architect, a
designer we work with, or a pre-approved plan where your city offers
one.
-
2
Permit review: if there's
an existing home on the lot, state law generally gives the city 60
days from a completed application to approve or deny it. If it
denies the application, it has to explain in writing what needs
fixing.
-
3
Construction and inspections:
the city inspects the work along the way, and a final inspection
closes out the permit.
What can add time:
-
An incomplete application or corrections to the plans.
-
Permit questions on an older garage or past unpermitted work.
-
Utility work, such as a panel upgrade.
-
A property in the coastal zone, or a historic property.
-
Special-order materials.
A conversion often has less to build than a new detached unit, but older
garages can bring surprises. We'll go over your schedule with you before
we start.
This article is general information, not legal advice. Rules vary by
property and city. Information as of November 2026.